CHALLENGES IN DESIGNING A WIND FARM ON AN ERODING BEACH ALONG THE DUTCH COAST. (2023). Coastal Engineering Proceedings, 37, sediment.2. https://doi.org/10.9753/icce.v37.sediment.2

Abstract

The Dutch energy company Eneco received the concession to construct a 116 MW windfarm on the Maasvlakte-2, a recent large seaward port extension of the Port of Rotterdam. The land reclamation is protected partly by a hard sea defence and partly by a soft sea defence, consisting of a sandy beach and adjacent dunes. Twelve wind turbines with a monopile foundation will be constructed on the beach, close to or in the waterline. The beach is erosive and is maintained by regular beach and foreshore nourishments. Designing and constructing wind turbines in this dynamic environment forms an unprecedented challenge.
PDF

References

LUFI (2021): Physical model tests to verify the design of a scour protection around monopiles in waves and currents, Gottfried Wilhelm Leibniz Universität Hannover

Creative Commons License

This work is licensed under a Creative Commons Attribution 4.0 International License.

Copyright (c) 2023 Anne de Beer, Marius Sokolewicz, Dirk Jan Peters, Jelmer IJntema, Arjen Luijendijk, Bas van Leeuwen, Arjan Hamoen