ANALYSIS AND PRELIMINARY DESIGN OF A TANGENT BORED PILE WALL AS AN ALTERNATIVE TO CONVENTIONAL BREAKWATERS
ICCE 2022
PDF

How to Cite

ANALYSIS AND PRELIMINARY DESIGN OF A TANGENT BORED PILE WALL AS AN ALTERNATIVE TO CONVENTIONAL BREAKWATERS. (2023). Coastal Engineering Proceedings, 37, structures.96. https://doi.org/10.9753/icce.v37.structures.96

Abstract

Based on existing construction practices, and the difficulty of sourcing rock armor materials in the Philippines, an alternative to conventional rubble mound breakwaters was considered for a beach resort development in Cebu, Philippines. A tangent bored pile wall, consisting of circular piles placed diametrically along a specified alignment, was analyzed and designed as a breakwater. It relies on pile embedment depth and soil friction for stability, unlike conventional breakwaters which rely on the weight of the armor rocks and the interlocking of individual armor units.
PDF

References

McConnell, K., Allsop, W. and Cruickshank, I. (2004): Piers, jetties, and related structures exposed to waves: Guidelines for hydraulic loadings, Thomas Telford Publishing, 1 Heron Quay, London.

U.S. Army Corps of Engineers. (2011): Coastal Engineering Manual, Washington, D.C. p. II-1-35.