Abstract

When the construction of the Zeebrugge Outer Harbour was finished a full scale monitoring system was realized as a part of the global monitoring and inspection programme. The monitoring system was designed to follow the water level- and the water pressure fluctuation inside and in front of the breakwater. A general description is given of the instrumentation of a section of the NW-breakwater followed by a global overview of the data-acquisition system and off-line data processing. Results from the primary analysis of the raw data of relevant storm measuring sessions are presented.
PDF
Authors retain copyright and grant the Proceedings right of first publication with the work simultaneously licensed under a Creative Commons Attribution License that allows others to share the work with an acknowledgement of the work's authorship and initial publication in this Proceedings.